This technique is used for work packages that have dependency on
other work packages. The work value of the dependent packages is
set as a fixed ratio to the
value of the parent work packages calculated using another method
(e.g. the milestone method). In
practice, this method is suitable e.g. for design reviews, reviews
of produced pieces, etc. (Source: Mehrmann/Wirtz)